PMI-ACP PMI Agile Certified Practitioner Exam
If you’re experienced using agile approaches, have good collaboration skills,
eagerly embrace complexity and thrive on rapid response times, then your talents
are in demand.
The PMI Agile Certified Practitioner (PMI-ACP)® formally recognizes your
knowledge of agile principles and your skill with agile techniques. It will make
you shine even brighter to your employers, stakeholders and peers.
The PMI-ACP® is our fastest growing certification, and it’s no wonder.
Organizations that are highly agile and responsive to market dynamics complete
more of their projects successfully than their slower-moving counterparts — 75
percent versus 56 percent — as shown in our 2015 Pulse of the Profession®
report.
The PMI-ACP spans many approaches to agile such as Scrum, Kanban, Lean, extreme
programming (XP) and test-driven development (TDD.) So it will increase your
versatility, wherever your projects may take you.
Take the PMI-ACP Exam Online Through an online proctor, you have the option to take the PMI-ACP exam from
home or your office—a great option to fit your busy lifestyle.
Who Should Apply? If you work on agile teams or if your organization is adopting agile
practices, the PMI-ACP is a good choice for you. Compared with other agile
certifications based solely on training and exams, the PMI-ACP is evidence of
your real-world, hands-on experience and skill.
Gain and Maintain Your PMI-ACP The certification exam has 120 multiple-choice questions and you have three
hours to complete it.
To maintain your PMI-ACP, you must earn 30 professional development units (PDUs)
in agile topics every three years.
Prerequisites 2,000 hours of general project experience working on teams. A current PMP®
or PgMP® will satisfy this requirement but is not required to apply for the
PMI-ACP.
1,500 hours working on agile project teams or with agile methodologies. This
requirement is in addition to the 2,000 hours of general project experience.
21 contact hours of training in agile practices.
QUESTION 1 What key benefits might stakeholders realize from an Agile approach?
A. The ability to bypass the change-management process, inserting new
requirements and changes directly into the team as they meet daily
B. The early and continuous delivery of valuable software, providing increased
visibility and the opportunity for more frequent adjustments
C. Increased access to the project and less reliance on formal reports and
status meetings to better understand the current work and the risks the team is
accepting
D. The team’s flexibility to make changes mid-iteration as business needs or
priorities change, increasing the ability of the team to meet project
commitments
Correct Answer: B
QUESTION 2 What is the first thing that a team should do to estimate user stories for a
project?
A. Sort the user stories according to priority.
B. Schedule a team meeting to understand them.
C. Define the story points measure.
D. Estimate through function point analysis.
Correct Answer: C
QUESTION 3 A story point is the:
A. Relative measure of the size of a user story.
B. Duration it takes to complete a user story.
C. Priority of the user story in the backlog.
D. Business value of the user story.
Correct Answer: A
QUESTION 4 According to the Agile Manifesto, which of the following describes the more
valued items?
A. Customer collaboration, following a plan, working software, and individual
interactions 07B13F58239056B81577933EB624485B
B. Working software, individual interactions, responding to change, and
comprehensive documentation
C. Individual interactions, working software, customer collaboration, and
responding to change
D. Responding to change, individual interactions, processes and tools, and
customercollaboration
Correct Answer: C
QUESTION 5 On a particular project, product quality is being measured at regular
intervals and is consistently below the acceptable level. In a Lean environment,
how should this problem be addressed?
A. The team should implement more rigorous testing at the end of each
development cycle.
B. Management should direct the team on specific actions that they should take
to improve quality.
C. Management should guide the team as it seeks to improve itself and reduce
errors in the system.
D. The Project Champion should review the acceptable quality threshold to ensure
that it is realistic.